Production Planning MTS Make to stock Scenario
Organization strcture
3000=Company code
3000=Plant
3000=Purchasing organization
3000=Sales organization
300=Warehouse
0001=Storage location
003=Purchasing group
3000=Shipping point
Business Process Steps for MTS no warehouse management in place
  1. Create PIR planned independent requirements
  2. Check stock & requirements list
  3. Run single item multi level MRP
  4. Convert planned order of raw material into purchase requisition
  5. Conver purchse requisition into purchase orders
  6. Receive raw material into storage location
  7. Convert planned order of finished product into production order
  8. Release the production order
  9. Issue input components to production order
  10. Confirmation of production order
  11. Goods receipt of final product into storage location
 
You need Flash Player in order to view this.
Products.avi
Products
 
You need Flash Player in order to view this.
BOM.avi
BOM
 
You need Flash Player in order to view this.
Work Center.avi
Work center
 
You need Flash Player in order to view this.
Routing.avi
Routing
 
You need Flash Player in order to view this.
Production Version.avi
Production version
 
You need Flash Player in order to view this.
PIR Planned independent requirements For MTS scenario.avi
Make to Stock MTS
 
You need Flash Player in order to view this.
MRP Run Material requirement planning.avi
MRP
 
You need Flash Player in order to view this.
Convert planned order to PR and PO of input components.avi
Convert planned order to PR and PO of input components.avi
 
You need Flash Player in order to view this.
Produce the final finished product.avi
Produce
 
 